LEE + RO to Design Two Replacement Lift Stations for the City of Riverside

Written by Amritendu Maji, PE | Mar 9, 2021 8:12:00 PM

The city of Riverside has contracted LEE + RO to prepare the construction documents for the replacement of two existing wastewater lift stations: Fairgrounds Street Lift Station and Dexter Drive Lift Station. Both of the existing lift stations were originally constructed in the late 1960s with a wet well manhole and a pump chamber vault with pedestal mounted pumps in a duplex (duty/standby) configuration.

The City’s objective is to replace each of the existing lift stations with a new lift station that conforms to the City’s current sewage lift station and force main guidelines that include wet well submersible pumps and valve vaults.
Improvements include:

Fairgrounds St. Lift Station

  • New 10-ft diameter x 20-ft deep wet well
  • Two new 280 gpm submersible pumps with new MCC
  • Upgraded electrical service from 230V to 480V
  • New valve vault
  • New 8-inch force main

Dexter Dr. Lift Station

  • New 10-ft diameter x 15-ft deep wet well
  • Two new 170 gpm submersible pumps with new MCC
  • Upgraded electrical service from 230V to 480V
  • New valve vault
  • New 8-inch force main

These projects improve the system’s overall performance, maintains reliability of the sewer system, and ensures that infrastructure meets the City’s current standards.